Accelerating transmission capacity expansion by using advanced conductors in existing right-of-way.


ABSTRACT: As countries pursue decarbonization goals, the rapid expansion of transmission capacity for renewable energy (RE) integration poses a significant challenge due to hurdles such as permitting and cost allocation. However, we find that large-scale reconductoring with advanced composite-core conductors can cost-effectively double transmission capacity within existing right-of-way, with limited additional permitting. This strategy unlocks a high availability of increasingly economically viable RE resources in close proximity to the existing network. We implement reconductoring in a model of the US power system, showing that reconductoring can help meet over 80% of the new interzonal transmission needed to reach over 90% clean electricity by 2035 given restrictions on greenfield transmission bui

SUBMITTER: Chojkiewicz E 

PROVIDER: S-EPMC11459140 | biostudies-literature | 2024 Oct

REPOSITORIES: biostudies-literature