Research on extremely short construction period of engineering project based on labor balance under resource tolerance.
Ontology highlight
ABSTRACT: Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dyn